Renovation & Alteration permits in ZIP 60625
The median renovation & alteration permit wait in ZIP 60625 was 33 days, based on 921 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60625, 921 issued permit records show a median processing time of 33 days; 75% were issued within 83 days and 90% within 175 days, covering January 2021 through September 15, 2026.
The median was 3 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60625: wait distribution
For Renovation & Alteration permits in ZIP 60625, 921 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60625: annual permit timing
Renovation & Alteration permits in ZIP 60625 has 6 publishable issue-year cohorts spanning 2021–2026, representing 921 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 167 | 3 days | 47 days | 102 days |
| 2022 | 199 | 2 days | 47 days | 141 days |
| 2023 | 159 | 34 days | 84 days | 140 days |
| 2024 | 157 | 49 days | 97 days | 185 days |
| 2025 | 125 | 58 days | 128 days | 220 days |
| 2026* | 114 | 62 days | 136 days | 210 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60625: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60625 has 921 issued records, a 33 days median, and a 83 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60625 comparisons
The Renovation & Alteration permits in ZIP 60625 cohort contains 921 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60625 permits ZIP reportRenovation & Alteration citywide Type report