New Construction permits in ZIP 60659
The median new construction permit wait in ZIP 60659 was 72 days, based on 40 issued records.
Records checked402021–Sep. 15, 2026
The short answer
Typical wait72 daysmedian issued permit
Usually within138 days75% of records
Long-wait edge205 days90% of records
Evidence40issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context