ZIP code × permit type
New Construction permits in ZIP 60659
The median new construction permit wait in ZIP 60659 was 72 days, based on 40 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60659, 40 issued permit records show a median processing time of 72 days; 75% were issued within 138 days and 90% within 205 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60659: wait distribution
For New Construction permits in ZIP 60659, 40 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60659: annual permit timing
New Construction permits in ZIP 60659 has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60659: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60659 has 40 issued records, a 72 days median, and a 138 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60659 comparisons
The New Construction permits in ZIP 60659 cohort contains 40 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60659 permits ZIP reportNew Construction citywide Type report