ZIP boundary report
Permit processing times in ZIP 60644
Across 2,688 issued permits assigned to ZIP 60644, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60644, 2,688 issued permit records show a median processing time of 1 day; 75% were issued within 18 days and 90% within 77 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Permit processing times in ZIP 60644: wait distribution
For Permit processing times in ZIP 60644, 2,688 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60644: annual permit timing
Permit processing times in ZIP 60644 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,688 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 516 | 0 days | 8 days | 77 days |
| 2022 | 505 | 0 days | 11 days | 69 days |
| 2023 | 478 | 0 days | 7.8 days | 68 days |
| 2024 | 459 | 7 days | 26 days | 77 days |
| 2025 | 438 | 5.5 days | 27 days | 81 days |
| 2026* | 292 | 6 days | 34 days | 97 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60644: ZIP codes with similar overall timing
Permit processing times in ZIP 60644 has 2,688 issued records, a 1 day median, and a 18 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60644 comparisons
The Permit processing times in ZIP 60644 cohort contains 2,688 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 33 daysEasy Permit Process 0 daysNew Construction 71 daysSigns 23 daysElevator Equipment 0 daysWrecking & Demolition 0 daysReinstated Permit 0 days