Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60644

The median express permit program permit wait in ZIP 60644 was 1 day, based on 1,165 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,1652021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60644, 1,165 issued permit records show a median processing time of 1 day; 75% were issued within 7 days and 90% within 22 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within7 days75% of records
Long-wait edge22 days90% of records
Evidence1,165issued permits

The median was 1 day faster than the previous 12 months.

Express Permit Program permits in ZIP 60644: wait distribution

For Express Permit Program permits in ZIP 60644, 1,165 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
43.9%
1–7 days
31.7%
8–30 days
18.2%
31–90 days
5.2%
91+ days
0.9%

Change over time

Express Permit Program permits in ZIP 60644: annual permit timing

Express Permit Program permits in ZIP 60644 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,165 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211350 days0 days7 days
20221220 days1 day22 days
20231240 days1 day11 days
20242962 days9 days21 days
20252893 days10 days27 days
2026*1993 days9 days21 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60644: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60644 has 1,165 issued records, a 1 day median, and a 7 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606021 day9 days1,021
ZIP 606031 day9 days1,124
ZIP 606051 day10 days1,055
ZIP 606081 day7 days1,903
ZIP 606091 day7 days1,621
ZIP 606121 day7 days1,543
ZIP 606131 day8 days1,095
ZIP 606141 day9 days2,934