ZIP code × permit type
New Construction permits in ZIP 60643
The median new construction permit wait in ZIP 60643 was 91 days, based on 68 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60643, 68 issued permit records show a median processing time of 91 days; 75% were issued within 160 days and 90% within 236 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60643: wait distribution
For New Construction permits in ZIP 60643, 68 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60643: annual permit timing
New Construction permits in ZIP 60643 has 2 publishable issue-year cohorts spanning 2025–2026, representing 36 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2025 | 18 | 98 days | 173 days | 275 days |
| 2026* | 18 | 91 days | 147 days | 175 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60643: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60643 has 68 issued records, a 91 days median, and a 160 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60643 comparisons
The New Construction permits in ZIP 60643 cohort contains 68 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60643 permits ZIP reportNew Construction citywide Type report