Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60643

Across 4,036 issued permits assigned to ZIP 60643, the median processing time was 1 day.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked4,0362021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60643, 4,036 issued permit records show a median processing time of 1 day; 75% were issued within 11 days and 90% within 57 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within11 days75% of records
Long-wait edge57 days90% of records
Evidence4,036issued permits

The median was 1 day slower than the previous 12 months.

Permit processing times in ZIP 60643: wait distribution

For Permit processing times in ZIP 60643, 4,036 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
49.4%
1–7 days
20.5%
8–30 days
16.2%
31–90 days
7.3%
91+ days
6.6%

Change over time

Permit processing times in ZIP 60643: annual permit timing

Permit processing times in ZIP 60643 has 6 publishable issue-year cohorts spanning 2021–2026, representing 4,036 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20217650 days6 days23 days
20227730 days8 days48 days
20236510 days11 days41 days
20246413 days17 days63 days
20256783 days19 days77 days
2026*5283 days13 days81 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60643: ZIP codes with similar overall timing

Permit processing times in ZIP 60643 has 4,036 issued records, a 1 day median, and a 11 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606021 day10 days1,991
606031 day13 days1,858
606051 day16 days2,380
606091 day21 days3,840
606121 day25 days3,771
606171 day11 days4,812
606191 day12 days5,016
606201 day11 days5,084