Wrecking & Demolition permits in ZIP 60643

The median wrecking & demolition permit wait in ZIP 60643 was 0 days, based on 61 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked612021–Sep. 15, 2026

The short answer

For Wrecking & Demolition permits in ZIP 60643, 61 issued permit records show a median processing time of 0 days; 75% were issued within 56 days and 90% within 96 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within56 days75% of records
Long-wait edge96 days90% of records
Evidence61issued permits

Not enough records for a year-over-year comparison.

Wrecking & Demolition permits in ZIP 60643: wait distribution

For Wrecking & Demolition permits in ZIP 60643, 61 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
57.4%
1–7 days
0.0%
8–30 days
4.9%
31–90 days
26.2%
91+ days
11.5%

Change over time

Wrecking & Demolition permits in ZIP 60643: annual permit timing

Wrecking & Demolition permits in ZIP 60643 has 3 publishable issue-year cohorts spanning 2021–2024, representing 39 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211749 days76 days98 days
2022110 days78 days129 days
2024110 days0 days0 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition permits in ZIP 60643: Wrecking & Demolition timing in comparable ZIP codes

Wrecking & Demolition permits in ZIP 60643 has 61 issued records, a 0 days median, and a 56 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606070 days70 days89
ZIP 606080 days64 days115
ZIP 606090 days48 days151
ZIP 606120 days58 days95
ZIP 606130 days51 days128
ZIP 606140 days60 days270
ZIP 606160 days55 days53
ZIP 606170 days24 days118