Renovation & Alteration permits in ZIP 60643
The median renovation & alteration permit wait in ZIP 60643 was 43 days, based on 556 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60643, 556 issued permit records show a median processing time of 43 days; 75% were issued within 108 days and 90% within 202 days, covering January 2021 through September 15, 2026.
The median was 16 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60643: wait distribution
For Renovation & Alteration permits in ZIP 60643, 556 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60643: annual permit timing
Renovation & Alteration permits in ZIP 60643 has 6 publishable issue-year cohorts spanning 2021–2026, representing 556 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 118 | 1 day | 54 days | 105 days |
| 2022 | 148 | 10 days | 66 days | 183 days |
| 2023 | 85 | 51 days | 109 days | 179 days |
| 2024 | 89 | 83 days | 144 days | 231 days |
| 2025 | 74 | 82 days | 172 days | 307 days |
| 2026* | 42 | 104 days | 156 days | 212 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60643: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60643 has 556 issued records, a 43 days median, and a 108 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60643 comparisons
The Renovation & Alteration permits in ZIP 60643 cohort contains 556 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60643 permits ZIP reportRenovation & Alteration citywide Type report