ZIP code × permit type
New Construction permits in ZIP 60605
The median new construction permit wait in ZIP 60605 was 1 day, based on 287 issued records.
Records checked2872021–Sep. 15, 2026
The short answer
Typical wait1 daymedian issued permit
Usually within10 days75% of records
Long-wait edge38 days90% of records
Evidence287issued permits
The median was 2 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 29 | 0 days | 0 days | 20 days |
| 2022 | 65 | 0 days | 1 day | 44 days |
| 2023 | 46 | 0 days | 3.8 days | 44 days |
| 2024 | 53 | 4 days | 14 days | 24 days |
| 2025 | 51 | 5 days | 12 days | 20 days |
| 2026* | 43 | 7 days | 22 days | 73 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.