New Construction permits in ZIP 60613
The median new construction permit wait in ZIP 60613 was 9 days, based on 232 issued records.
Records checked2322021–Sep. 15, 2026
The short answer
Typical wait9 daysmedian issued permit
Usually within67 days75% of records
Long-wait edge161 days90% of records
Evidence232issued permits
The median was 10 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 37 | 0 days | 9 days | 93 days |
| 2022 | 42 | 0 days | 7.5 days | 91 days |
| 2023 | 43 | 15 days | 68 days | 179 days |
| 2024 | 28 | 34 days | 92 days | 166 days |
| 2025 | 37 | 26 days | 95 days | 152 days |
| 2026* | 45 | 27 days | 63 days | 167 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context