New Construction permits in ZIP 60613
The median new construction permit wait in ZIP 60613 was 9 days, based on 232 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60613, 232 issued permit records show a median processing time of 9 days; 75% were issued within 67 days and 90% within 161 days, covering January 2021 through September 15, 2026.
The median was 10 days faster than the previous 12 months.
New Construction permits in ZIP 60613: wait distribution
For New Construction permits in ZIP 60613, 232 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60613: annual permit timing
New Construction permits in ZIP 60613 has 6 publishable issue-year cohorts spanning 2021–2026, representing 232 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 37 | 0 days | 9 days | 93 days |
| 2022 | 42 | 0 days | 7.5 days | 91 days |
| 2023 | 43 | 15 days | 68 days | 179 days |
| 2024 | 28 | 34 days | 92 days | 166 days |
| 2025 | 37 | 26 days | 95 days | 152 days |
| 2026* | 45 | 27 days | 63 days | 167 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60613: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60613 has 232 issued records, a 9 days median, and a 67 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60613 comparisons
The New Construction permits in ZIP 60613 cohort contains 232 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60613 permits ZIP reportNew Construction citywide Type report