New Construction permits in ZIP 60610
The median new construction permit wait in ZIP 60610 was 6 days, based on 126 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60610, 126 issued permit records show a median processing time of 6 days; 75% were issued within 42 days and 90% within 168 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60610: wait distribution
For New Construction permits in ZIP 60610, 126 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60610: annual permit timing
New Construction permits in ZIP 60610 has 6 publishable issue-year cohorts spanning 2021–2026, representing 126 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 27 | 0 days | 23 days | 79 days |
| 2022 | 34 | 15 days | 40 days | 104 days |
| 2023 | 19 | 0 days | 24 days | 49 days |
| 2024 | 16 | 6 days | 573 days | 574 days |
| 2025 | 14 | 7 days | 77 days | 149 days |
| 2026* | 16 | 27 days | 72 days | 186 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60610: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60610 has 126 issued records, a 6 days median, and a 42 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60610 comparisons
The New Construction permits in ZIP 60610 cohort contains 126 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60610 permits ZIP reportNew Construction citywide Type report