New Construction permits in ZIP 60610
The median new construction permit wait in ZIP 60610 was 6 days, based on 126 issued records.
Records checked1262021–Sep. 15, 2026
The short answer
Typical wait6 daysmedian issued permit
Usually within42 days75% of records
Long-wait edge168 days90% of records
Evidence126issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 27 | 0 days | 23 days | 79 days |
| 2022 | 34 | 15 days | 40 days | 104 days |
| 2023 | 19 | 0 days | 24 days | 49 days |
| 2024 | 16 | 6 days | 573 days | 574 days |
| 2025 | 14 | 7 days | 77 days | 149 days |
| 2026* | 16 | 27 days | 72 days | 186 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context