New Construction permits in ZIP 60607
The median new construction permit wait in ZIP 60607 was 15 days, based on 319 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60607, 319 issued permit records show a median processing time of 15 days; 75% were issued within 70 days and 90% within 131 days, covering January 2021 through September 15, 2026.
The median was 39 days faster than the previous 12 months.
New Construction permits in ZIP 60607: wait distribution
For New Construction permits in ZIP 60607, 319 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60607: annual permit timing
New Construction permits in ZIP 60607 has 6 publishable issue-year cohorts spanning 2021–2026, representing 319 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 60 | 6.5 days | 63 days | 116 days |
| 2022 | 84 | 20 days | 58 days | 124 days |
| 2023 | 55 | 9 days | 40 days | 110 days |
| 2024 | 42 | 12 days | 67 days | 132 days |
| 2025 | 43 | 39 days | 96 days | 263 days |
| 2026* | 35 | 6 days | 70 days | 122 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60607: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60607 has 319 issued records, a 15 days median, and a 70 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60607 comparisons
The New Construction permits in ZIP 60607 cohort contains 319 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60607 permits ZIP reportNew Construction citywide Type report