New Construction permits in ZIP 60607
The median new construction permit wait in ZIP 60607 was 15 days, based on 319 issued records.
Records checked3192021–Sep. 15, 2026
The short answer
Typical wait15 daysmedian issued permit
Usually within70 days75% of records
Long-wait edge131 days90% of records
Evidence319issued permits
The median was 39 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 60 | 6.5 days | 63 days | 116 days |
| 2022 | 84 | 20 days | 58 days | 124 days |
| 2023 | 55 | 9 days | 40 days | 110 days |
| 2024 | 42 | 12 days | 67 days | 132 days |
| 2025 | 43 | 39 days | 96 days | 263 days |
| 2026* | 35 | 6 days | 70 days | 122 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.