New Construction permits in ZIP 60622
The median new construction permit wait in ZIP 60622 was 15 days, based on 292 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60622, 292 issued permit records show a median processing time of 15 days; 75% were issued within 91 days and 90% within 200 days, covering January 2021 through September 15, 2026.
The median was 30 days slower than the previous 12 months.
New Construction permits in ZIP 60622: wait distribution
For New Construction permits in ZIP 60622, 292 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60622: annual permit timing
New Construction permits in ZIP 60622 has 6 publishable issue-year cohorts spanning 2021–2026, representing 292 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 62 | 0 days | 24 days | 98 days |
| 2022 | 73 | 0 days | 6 days | 215 days |
| 2023 | 44 | 22 days | 65 days | 202 days |
| 2024 | 34 | 66 days | 194 days | 276 days |
| 2025 | 38 | 42 days | 98 days | 205 days |
| 2026* | 41 | 75 days | 142 days | 176 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60622: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60622 has 292 issued records, a 15 days median, and a 91 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60622 comparisons
The New Construction permits in ZIP 60622 cohort contains 292 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60622 permits ZIP reportNew Construction citywide Type report