New Construction permits in ZIP 60622
The median new construction permit wait in ZIP 60622 was 15 days, based on 292 issued records.
Records checked2922021–Sep. 15, 2026
The short answer
Typical wait15 daysmedian issued permit
Usually within91 days75% of records
Long-wait edge200 days90% of records
Evidence292issued permits
The median was 30 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 62 | 0 days | 24 days | 98 days |
| 2022 | 73 | 0 days | 6 days | 215 days |
| 2023 | 44 | 22 days | 65 days | 202 days |
| 2024 | 34 | 66 days | 194 days | 276 days |
| 2025 | 38 | 42 days | 98 days | 205 days |
| 2026* | 41 | 75 days | 142 days | 176 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.