Renovation & Alteration permits in ZIP 60602
The median renovation & alteration permit wait in ZIP 60602 was 0 days, based on 254 issued records.
Records checked2542021–Sep. 15, 2026
The short answer
Typical wait0 daysmedian issued permit
Usually within19 days75% of records
Long-wait edge57 days90% of records
Evidence254issued permits
The median was 13 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 50 | 0 days | 0 days | 54 days |
| 2022 | 73 | 0 days | 0 days | 0 days |
| 2023 | 40 | 0 days | 12 days | 46 days |
| 2024 | 37 | 23 days | 43 days | 71 days |
| 2025 | 29 | 19 days | 49 days | 103 days |
| 2026* | 25 | 11 days | 21 days | 67 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.