Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60634

The median express permit program permit wait in ZIP 60634 was 0 days, based on 1,746 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,7462021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60634, 1,746 issued permit records show a median processing time of 0 days; 75% were issued within 5 days and 90% within 14 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within5 days75% of records
Long-wait edge14 days90% of records
Evidence1,746issued permits

The median was unchanged from the previous 12 months.

Express Permit Program permits in ZIP 60634: wait distribution

For Express Permit Program permits in ZIP 60634, 1,746 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
51.9%
1–7 days
29.9%
8–30 days
14.3%
31–90 days
3.0%
91+ days
0.9%

Change over time

Express Permit Program permits in ZIP 60634: annual permit timing

Express Permit Program permits in ZIP 60634 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,746 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212010 days3 days18 days
20221820 days0 days6.9 days
20231690 days2 days8.4 days
20244751 day6 days14 days
20254341 day6 days13 days
2026*2851 day7 days16 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60634: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60634 has 1,746 issued records, a 0 days median, and a 5 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606170 days6 days2,669
ZIP 606290 days5 days2,533
ZIP 606300 days6 days1,548
ZIP 606310 days8 days1,681
ZIP 606330 days2 days751
ZIP 606340 days5 days1,746
ZIP 606380 days6 days1,510
ZIP 606390 days6 days1,425