Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60630

The median express permit program permit wait in ZIP 60630 was 0 days, based on 1,548 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,5482021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60630, 1,548 issued permit records show a median processing time of 0 days; 75% were issued within 6 days and 90% within 18 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within6 days75% of records
Long-wait edge18 days90% of records
Evidence1,548issued permits

The median was 2 days faster than the previous 12 months.

Express Permit Program permits in ZIP 60630: wait distribution

For Express Permit Program permits in ZIP 60630, 1,548 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
51.1%
1–7 days
29.1%
8–30 days
15.0%
31–90 days
3.7%
91+ days
1.0%

Change over time

Express Permit Program permits in ZIP 60630: annual permit timing

Express Permit Program permits in ZIP 60630 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,548 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211840 days0 days11 days
20221690 days0 days8 days
20231690 days4 days24 days
20243891 day7 days15 days
20253712 days7 days22 days
2026*2661 day8 days19 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60630: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60630 has 1,548 issued records, a 0 days median, and a 6 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606170 days6 days2,669
ZIP 606290 days5 days2,533
ZIP 606300 days6 days1,548
ZIP 606310 days8 days1,681
ZIP 606330 days2 days751
ZIP 606340 days5 days1,746
ZIP 606380 days6 days1,510
ZIP 606390 days6 days1,425