ZIP boundary report
Permit processing times in ZIP 60630
Across 3,322 issued permits assigned to ZIP 60630, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60630, 3,322 issued permit records show a median processing time of 1 day; 75% were issued within 13 days and 90% within 60 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Permit processing times in ZIP 60630: wait distribution
For Permit processing times in ZIP 60630, 3,322 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60630: annual permit timing
Permit processing times in ZIP 60630 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,322 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 636 | 0 days | 4 days | 41 days |
| 2022 | 658 | 0 days | 7 days | 55 days |
| 2023 | 581 | 0 days | 11 days | 55 days |
| 2024 | 551 | 4 days | 21 days | 65 days |
| 2025 | 526 | 5 days | 27 days | 72 days |
| 2026* | 370 | 6 days | 24 days | 63 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60630: ZIP codes with similar overall timing
Permit processing times in ZIP 60630 has 3,322 issued records, a 1 day median, and a 13 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60630 comparisons
The Permit processing times in ZIP 60630 cohort contains 3,322 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 0 daysEasy Permit Process 0 daysRenovation & Alteration 41 daysSigns 16 daysNew Construction 35 daysWrecking & Demolition 0 daysElevator Equipment 0 days