ZIP code × permit type

Renovation & Alteration permits in ZIP 60636

The median renovation & alteration permit wait in ZIP 60636 was 45 days, based on 596 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked5962021–Sep. 15, 2026

The short answer

For Renovation & Alteration permits in ZIP 60636, 596 issued permit records show a median processing time of 45 days; 75% were issued within 112 days and 90% within 214 days, covering January 2021 through September 15, 2026.

Typical wait45 daysmedian issued permit
Usually within112 days75% of records
Long-wait edge214 days90% of records
Evidence596issued permits

The median was 18 days slower than the previous 12 months.

Renovation & Alteration permits in ZIP 60636: wait distribution

For Renovation & Alteration permits in ZIP 60636, 596 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
12.9%
1–7 days
15.9%
8–30 days
13.1%
31–90 days
27.7%
91+ days
30.4%

Change over time

Renovation & Alteration permits in ZIP 60636: annual permit timing

Renovation & Alteration permits in ZIP 60636 has 6 publishable issue-year cohorts spanning 2021–2026, representing 596 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211206 days50 days118 days
202211810 days86 days209 days
20239235 days93 days162 days
20249664 days133 days222 days
202510580 days149 days255 days
2026*65101 days181 days280 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration permits in ZIP 60636: Renovation & Alteration timing in comparable ZIP codes

Renovation & Alteration permits in ZIP 60636 has 596 issued records, a 45 days median, and a 112 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6063645 days112 days596
ZIP 6062344 days107 days972
ZIP 6063443 days109 days457
ZIP 6064343 days108 days556
ZIP 6070743 days106 days152
ZIP 6060842 days115 days1,029
ZIP 6062242 days100 days1,099
ZIP 6064648 days110 days327