Renovation & Alteration permits in ZIP 60659

The median renovation & alteration permit wait in ZIP 60659 was 50 days, based on 306 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked3062021–Sep. 15, 2026

The short answer

For Renovation & Alteration permits in ZIP 60659, 306 issued permit records show a median processing time of 50 days; 75% were issued within 118 days and 90% within 254 days, covering January 2021 through September 15, 2026.

Typical wait50 daysmedian issued permit
Usually within118 days75% of records
Long-wait edge254 days90% of records
Evidence306issued permits

The median was 21 days slower than the previous 12 months.

Renovation & Alteration permits in ZIP 60659: wait distribution

For Renovation & Alteration permits in ZIP 60659, 306 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
16.7%
1–7 days
11.4%
8–30 days
11.8%
31–90 days
26.1%
91+ days
34.0%

Change over time

Renovation & Alteration permits in ZIP 60659: annual permit timing

Renovation & Alteration permits in ZIP 60659 has 6 publishable issue-year cohorts spanning 2021–2026, representing 306 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20216030 days103 days179 days
2022593 days58 days132 days
20236059 days146 days352 days
20245670 days174 days257 days
20254664 days120 days214 days
2026*25103 days160 days230 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration permits in ZIP 60659: Renovation & Alteration timing in comparable ZIP codes

Renovation & Alteration permits in ZIP 60659 has 306 issued records, a 50 days median, and a 118 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6065950 days118 days306
ZIP 6063249 days112 days485
ZIP 6065252 days116 days202
ZIP 6063952 days116 days485
ZIP 6064648 days110 days327
ZIP 6063645 days112 days596
ZIP 6062344 days107 days972
ZIP 6063443 days109 days457