ZIP code × permit type
Renovation & Alteration permits in ZIP 60639
The median renovation & alteration permit wait in ZIP 60639 was 52 days, based on 485 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60639, 485 issued permit records show a median processing time of 52 days; 75% were issued within 116 days and 90% within 216 days, covering January 2021 through September 15, 2026.
The median was 17 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60639: wait distribution
For Renovation & Alteration permits in ZIP 60639, 485 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60639: annual permit timing
Renovation & Alteration permits in ZIP 60639 has 6 publishable issue-year cohorts spanning 2021–2026, representing 485 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 101 | 15 days | 78 days | 144 days |
| 2022 | 90 | 22 days | 89 days | 248 days |
| 2023 | 97 | 52 days | 111 days | 241 days |
| 2024 | 85 | 63 days | 121 days | 243 days |
| 2025 | 70 | 66 days | 153 days | 210 days |
| 2026* | 42 | 90 days | 164 days | 216 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60639: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60639 has 485 issued records, a 52 days median, and a 116 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60639 comparisons
The Renovation & Alteration permits in ZIP 60639 cohort contains 485 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60639 permits ZIP reportRenovation & Alteration citywide Type report