Renovation & Alteration permits in ZIP 60652
The median renovation & alteration permit wait in ZIP 60652 was 52 days, based on 202 issued records.
Records checked2022021–Sep. 15, 2026
The short answer
Typical wait52 daysmedian issued permit
Usually within116 days75% of records
Long-wait edge203 days90% of records
Evidence202issued permits
The median was 20 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 41 | 28 days | 95 days | 175 days |
| 2022 | 41 | 4 days | 76 days | 185 days |
| 2023 | 42 | 54 days | 96 days | 131 days |
| 2024 | 32 | 76 days | 128 days | 188 days |
| 2025 | 26 | 78 days | 154 days | 333 days |
| 2026* | 20 | 100 days | 140 days | 233 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.