Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Wrecking & Demolition permits in ZIP 60621

The median wrecking & demolition permit wait in ZIP 60621 was 0 days, based on 167 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1672021–Sep. 15, 2026

The short answer

For Wrecking & Demolition permits in ZIP 60621, 167 issued permit records show a median processing time of 0 days; 75% were issued within 57 days and 90% within 151 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within57 days75% of records
Long-wait edge151 days90% of records
Evidence167issued permits

Not enough records for a year-over-year comparison.

Wrecking & Demolition permits in ZIP 60621: wait distribution

For Wrecking & Demolition permits in ZIP 60621, 167 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
58.7%
1–7 days
0.6%
8–30 days
3.6%
31–90 days
18.6%
91+ days
18.6%

Change over time

Wrecking & Demolition permits in ZIP 60621: annual permit timing

Wrecking & Demolition permits in ZIP 60621 has 6 publishable issue-year cohorts spanning 2021–2026, representing 167 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20215757 days145 days228 days
2022260 days80 days199 days
2023240 days0 days0 days
2024190 days0 days0 days
2025280 days0 days0 days
2026*1351 days60 days96 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition permits in ZIP 60621: Wrecking & Demolition timing in comparable ZIP codes

Wrecking & Demolition permits in ZIP 60621 has 167 issued records, a 0 days median, and a 57 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606070 days70 days89
ZIP 606080 days64 days115
ZIP 606090 days48 days151
ZIP 606120 days58 days95
ZIP 606130 days51 days128
ZIP 606140 days60 days270
ZIP 606160 days55 days53
ZIP 606170 days24 days118