Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Signs permits in ZIP 60621

The median signs permit wait in ZIP 60621 was 16 days, based on 82 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked822021–Sep. 15, 2026

The short answer

For Signs permits in ZIP 60621, 82 issued permit records show a median processing time of 16 days; 75% were issued within 54 days and 90% within 177 days, covering January 2021 through September 15, 2026.

Typical wait16 daysmedian issued permit
Usually within54 days75% of records
Long-wait edge177 days90% of records
Evidence82issued permits

Not enough records for a year-over-year comparison.

Signs permits in ZIP 60621: wait distribution

For Signs permits in ZIP 60621, 82 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
7.3%
1–7 days
20.7%
8–30 days
34.1%
31–90 days
19.5%
91+ days
18.3%

Change over time

Signs permits in ZIP 60621: annual permit timing

Signs permits in ZIP 60621 has 3 publishable issue-year cohorts spanning 2021–2025, representing 62 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021128 days16 days209 days
20233211 days13 days36 days
202518108 days178 days196 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in ZIP 60621: Signs timing in comparable ZIP codes

Signs permits in ZIP 60621 has 82 issued records, a 16 days median, and a 54 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6062116 days54 days82
ZIP 6062616 days52 days172
ZIP 6063016 days43 days217
ZIP 6063916 days49 days274
ZIP 6064216 days49 days512
ZIP 6064315 days40 days184
ZIP 6065117 days41 days186
ZIP 6065915 days46 days221