Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60607

The median express permit program permit wait in ZIP 60607 was 2 days, based on 1,882 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,8822021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60607, 1,882 issued permit records show a median processing time of 2 days; 75% were issued within 14 days and 90% within 35 days, covering January 2021 through September 15, 2026.

Typical wait2 daysmedian issued permit
Usually within14 days75% of records
Long-wait edge35 days90% of records
Evidence1,882issued permits

The median was unchanged from the previous 12 months.

Express Permit Program permits in ZIP 60607: wait distribution

For Express Permit Program permits in ZIP 60607, 1,882 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
37.6%
1–7 days
30.7%
8–30 days
20.2%
31–90 days
8.8%
91+ days
2.8%

Change over time

Express Permit Program permits in ZIP 60607: annual permit timing

Express Permit Program permits in ZIP 60607 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,882 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212950 days10 days34 days
20223421 day22 days48 days
20233541 day18 days48 days
20243263 days16 days40 days
20253313 days9 days19 days
2026*2343 days10 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60607: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60607 has 1,882 issued records, a 2 days median, and a 14 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606062 days20 days4,573
ZIP 606072 days14 days1,882
ZIP 606152 days10 days1,197
ZIP 606162 days9 days1,147
ZIP 606422 days10 days752
ZIP 606492 days9 days1,136
ZIP 606542 days15 days1,397
ZIP 606602 days8 days732