Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60660

The median express permit program permit wait in ZIP 60660 was 2 days, based on 732 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked7322021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60660, 732 issued permit records show a median processing time of 2 days; 75% were issued within 8 days and 90% within 20 days, covering January 2021 through September 15, 2026.

Typical wait2 daysmedian issued permit
Usually within8 days75% of records
Long-wait edge20 days90% of records
Evidence732issued permits

The median was 2 days slower than the previous 12 months.

Express Permit Program permits in ZIP 60660: wait distribution

For Express Permit Program permits in ZIP 60660, 732 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
38.9%
1–7 days
34.3%
8–30 days
20.8%
31–90 days
4.9%
91+ days
1.1%

Change over time

Express Permit Program permits in ZIP 60660: annual permit timing

Express Permit Program permits in ZIP 60660 has 6 publishable issue-year cohorts spanning 2021–2026, representing 732 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021980 days4.8 days16 days
2022580 days9 days30 days
2023720 days8.2 days28 days
20241862 days8 days19 days
20251922 days8 days19 days
2026*1264 days9 days32 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60660: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60660 has 732 issued records, a 2 days median, and a 8 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606062 days20 days4,573
ZIP 606072 days14 days1,882
ZIP 606152 days10 days1,197
ZIP 606162 days9 days1,147
ZIP 606422 days10 days752
ZIP 606492 days9 days1,136
ZIP 606542 days15 days1,397
ZIP 606602 days8 days732