ZIP code × permit type
Express Permit Program permits in ZIP 60616
The median express permit program permit wait in ZIP 60616 was 2 days, based on 1,147 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60616, 1,147 issued permit records show a median processing time of 2 days; 75% were issued within 9 days and 90% within 27 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Express Permit Program permits in ZIP 60616: wait distribution
For Express Permit Program permits in ZIP 60616, 1,147 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60616: annual permit timing
Express Permit Program permits in ZIP 60616 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,147 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 136 | 0 days | 6 days | 24 days |
| 2022 | 112 | 0 days | 20 days | 48 days |
| 2023 | 106 | 0 days | 4.8 days | 24 days |
| 2024 | 266 | 2 days | 8 days | 21 days |
| 2025 | 310 | 3 days | 13 days | 27 days |
| 2026* | 217 | 3 days | 9 days | 24 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60616: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60616 has 1,147 issued records, a 2 days median, and a 9 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60616 comparisons
The Express Permit Program permits in ZIP 60616 cohort contains 1,147 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60616 permits ZIP reportExpress Permit Program citywide Type report