Express Permit Program permits in ZIP 60604
The median express permit program permit wait in ZIP 60604 was 4 days, based on 677 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60604, 677 issued permit records show a median processing time of 4 days; 75% were issued within 15 days and 90% within 40 days, covering January 2021 through September 15, 2026.
The median was 2 days faster than the previous 12 months.
Express Permit Program permits in ZIP 60604: wait distribution
For Express Permit Program permits in ZIP 60604, 677 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60604: annual permit timing
Express Permit Program permits in ZIP 60604 has 6 publishable issue-year cohorts spanning 2021–2026, representing 677 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 145 | 2 days | 20 days | 40 days |
| 2022 | 109 | 7 days | 37 days | 83 days |
| 2023 | 130 | 4 days | 25 days | 53 days |
| 2024 | 136 | 5 days | 15 days | 32 days |
| 2025 | 101 | 4 days | 7 days | 15 days |
| 2026* | 56 | 1 day | 6.2 days | 14 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60604: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60604 has 677 issued records, a 4 days median, and a 15 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60604 comparisons
The Express Permit Program permits in ZIP 60604 cohort contains 677 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60604 permits ZIP reportExpress Permit Program citywide Type report