Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Wrecking & Demolition permits in ZIP 60610

The median wrecking & demolition permit wait in ZIP 60610 was 43 days, based on 32 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked322021–Sep. 15, 2026

The short answer

For Wrecking & Demolition permits in ZIP 60610, 32 issued permit records show a median processing time of 43 days; 75% were issued within 102 days and 90% within 159 days, covering January 2021 through September 15, 2026.

Typical wait43 daysmedian issued permit
Usually within102 days75% of records
Long-wait edge159 days90% of records
Evidence32issued permits

Not enough records for a year-over-year comparison.

Wrecking & Demolition permits in ZIP 60610: wait distribution

For Wrecking & Demolition permits in ZIP 60610, 32 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
46.9%
1–7 days
0.0%
8–30 days
0.0%
31–90 days
18.8%
91+ days
34.4%

Change over time

Wrecking & Demolition permits in ZIP 60610: annual permit timing

Wrecking & Demolition permits in ZIP 60610 has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition permits in ZIP 60610: Wrecking & Demolition timing in comparable ZIP codes

Wrecking & Demolition permits in ZIP 60610 has 32 issued records, a 43 days median, and a 102 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6061043 days102 days32
ZIP 606462 days100 days27
ZIP 606070 days70 days89
ZIP 606080 days64 days115
ZIP 606090 days48 days151
ZIP 606120 days58 days95
ZIP 606130 days51 days128
ZIP 606140 days60 days270