Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Renovation & Alteration permits in ZIP 60827

The median renovation & alteration permit wait in ZIP 60827 was 92 days, based on 51 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked512021–Sep. 15, 2026

The short answer

For Renovation & Alteration permits in ZIP 60827, 51 issued permit records show a median processing time of 92 days; 75% were issued within 93 days and 90% within 93 days, covering January 2021 through September 15, 2026.

Typical wait92 daysmedian issued permit
Usually within93 days75% of records
Long-wait edge93 days90% of records
Evidence51issued permits

Not enough records for a year-over-year comparison.

Renovation & Alteration permits in ZIP 60827: wait distribution

For Renovation & Alteration permits in ZIP 60827, 51 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
15.7%
1–7 days
2.0%
8–30 days
3.9%
31–90 days
13.7%
91+ days
64.7%

Change over time

Renovation & Alteration permits in ZIP 60827: annual permit timing

Renovation & Alteration permits in ZIP 60827 has 1 publishable issue-year cohorts spanning 2022–2022, representing 36 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20223692 days93 days93 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration permits in ZIP 60827: Renovation & Alteration timing in comparable ZIP codes

Renovation & Alteration permits in ZIP 60827 has 51 issued records, a 92 days median, and a 93 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6082792 days93 days51
ZIP 6063952 days116 days485
ZIP 6065252 days116 days202
ZIP 6065950 days118 days306
ZIP 6063249 days112 days485
ZIP 6064648 days110 days327
ZIP 6063645 days112 days596
ZIP 6062344 days107 days972