Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60827

Across 192 issued permits assigned to ZIP 60827, the median processing time was 7 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1922021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60827, 192 issued permit records show a median processing time of 7 days; 75% were issued within 72 days and 90% within 93 days, covering January 2021 through September 15, 2026.

Typical wait7 daysmedian issued permit
Usually within72 days75% of records
Long-wait edge93 days90% of records
Evidence192issued permits

Not enough records for a year-over-year comparison.

Permit processing times in ZIP 60827: wait distribution

For Permit processing times in ZIP 60827, 192 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
38.5%
1–7 days
14.6%
8–30 days
14.1%
31–90 days
10.9%
91+ days
21.9%

Change over time

Permit processing times in ZIP 60827: annual permit timing

Permit processing times in ZIP 60827 has 5 publishable issue-year cohorts spanning 2021–2026, representing 183 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021477 days18 days73 days
20226934 days92 days93 days
2023200 days9.8 days21 days
2025236 days17 days86 days
2026*2424 days49 days94 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60827: ZIP codes with similar overall timing

Permit processing times in ZIP 60827 has 192 issued records, a 7 days median, and a 72 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
608277 days72 days192
606425 days29 days2,425
606074 days28 days4,911
606104 days25 days3,503
606114 days15 days7,470
606224 days31 days4,440
606534 days29 days2,085
606544 days27 days3,185