Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60657

Across 5,111 issued permits assigned to ZIP 60657, the median processing time was 2 days.

Records checked5,1112021–Sep. 15, 2026

The short answer

Typical wait2 daysmedian issued permit
Usually within24 days75% of records
Long-wait edge82 days90% of records
Evidence5,111issued permits

The median was 1.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
41.4%
1–7 days
20.3%
8–30 days
16.3%
31–90 days
13.1%
91+ days
9.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211,0410 days10 days69 days
20229740 days10 days65 days
20238700 days19 days69 days
20248237 days29 days76 days
20258048 days40 days92 days
2026*59910 days42 days110 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

ZIP codes with similar overall timing

ReportMedian75% withinRecords
606062 days15 days6,775
606082 days26 days4,677
606132 days21 days2,994
606162 days25 days2,939
606182 days27 days6,576
606212 days23 days2,516
606232 days24 days4,182
606242 days21 days2,944