Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60657

Across 5,111 issued permits assigned to ZIP 60657, the median processing time was 2 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked5,1112021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60657, 5,111 issued permit records show a median processing time of 2 days; 75% were issued within 24 days and 90% within 82 days, covering January 2021 through September 15, 2026.

Typical wait2 daysmedian issued permit
Usually within24 days75% of records
Long-wait edge82 days90% of records
Evidence5,111issued permits

The median was 1.5 days slower than the previous 12 months.

Permit processing times in ZIP 60657: wait distribution

For Permit processing times in ZIP 60657, 5,111 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
41.4%
1–7 days
20.3%
8–30 days
16.3%
31–90 days
13.1%
91+ days
9.0%

Change over time

Permit processing times in ZIP 60657: annual permit timing

Permit processing times in ZIP 60657 has 6 publishable issue-year cohorts spanning 2021–2026, representing 5,111 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211,0410 days10 days69 days
20229740 days10 days65 days
20238700 days19 days69 days
20248237 days29 days76 days
20258048 days40 days92 days
2026*59910 days42 days110 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60657: ZIP codes with similar overall timing

Permit processing times in ZIP 60657 has 5,111 issued records, a 2 days median, and a 24 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606062 days15 days6,775
606082 days26 days4,677
606132 days21 days2,994
606162 days25 days2,939
606182 days27 days6,576
606212 days23 days2,516
606232 days24 days4,182
606242 days21 days2,944