ZIP code × permit type
New Construction permits in ZIP 60657
The median new construction permit wait in ZIP 60657 was 36 days, based on 325 issued records.
Records checked3252021–Sep. 15, 2026
The short answer
Typical wait36 daysmedian issued permit
Usually within80 days75% of records
Long-wait edge193 days90% of records
Evidence325issued permits
The median was 14 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 46 | 0 days | 16 days | 66 days |
| 2022 | 61 | 0 days | 14 days | 111 days |
| 2023 | 66 | 34 days | 105 days | 326 days |
| 2024 | 63 | 47 days | 96 days | 189 days |
| 2025 | 50 | 68 days | 114 days | 178 days |
| 2026* | 39 | 67 days | 106 days | 202 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.