ZIP code × permit type
New Construction permits in ZIP 60657
The median new construction permit wait in ZIP 60657 was 36 days, based on 325 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60657, 325 issued permit records show a median processing time of 36 days; 75% were issued within 80 days and 90% within 193 days, covering January 2021 through September 15, 2026.
The median was 14 days slower than the previous 12 months.
New Construction permits in ZIP 60657: wait distribution
For New Construction permits in ZIP 60657, 325 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60657: annual permit timing
New Construction permits in ZIP 60657 has 6 publishable issue-year cohorts spanning 2021–2026, representing 325 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 46 | 0 days | 16 days | 66 days |
| 2022 | 61 | 0 days | 14 days | 111 days |
| 2023 | 66 | 34 days | 105 days | 326 days |
| 2024 | 63 | 47 days | 96 days | 189 days |
| 2025 | 50 | 68 days | 114 days | 178 days |
| 2026* | 39 | 67 days | 106 days | 202 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60657: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60657 has 325 issued records, a 36 days median, and a 80 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60657 comparisons
The New Construction permits in ZIP 60657 cohort contains 325 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60657 permits ZIP reportNew Construction citywide Type report