ZIP code × permit type
New Construction permits in ZIP 60628
The median new construction permit wait in ZIP 60628 was 32 days, based on 83 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60628, 83 issued permit records show a median processing time of 32 days; 75% were issued within 100 days and 90% within 161 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60628: wait distribution
For New Construction permits in ZIP 60628, 83 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60628: annual permit timing
New Construction permits in ZIP 60628 has 3 publishable issue-year cohorts spanning 2021–2025, representing 60 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 21 | 0 days | 3 days | 66 days |
| 2023 | 18 | 32 days | 32 days | 129 days |
| 2025 | 21 | 81 days | 107 days | 128 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60628: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60628 has 83 issued records, a 32 days median, and a 100 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60628 comparisons
The New Construction permits in ZIP 60628 cohort contains 83 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60628 permits ZIP reportNew Construction citywide Type report