Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

New Construction permits in ZIP 60628

The median new construction permit wait in ZIP 60628 was 32 days, based on 83 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked832021–Sep. 15, 2026

The short answer

For New Construction permits in ZIP 60628, 83 issued permit records show a median processing time of 32 days; 75% were issued within 100 days and 90% within 161 days, covering January 2021 through September 15, 2026.

Typical wait32 daysmedian issued permit
Usually within100 days75% of records
Long-wait edge161 days90% of records
Evidence83issued permits

Not enough records for a year-over-year comparison.

New Construction permits in ZIP 60628: wait distribution

For New Construction permits in ZIP 60628, 83 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
22.9%
1–7 days
9.6%
8–30 days
13.3%
31–90 days
22.9%
91+ days
31.3%

Change over time

New Construction permits in ZIP 60628: annual permit timing

New Construction permits in ZIP 60628 has 3 publishable issue-year cohorts spanning 2021–2025, representing 60 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021210 days3 days66 days
20231832 days32 days129 days
20252181 days107 days128 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction permits in ZIP 60628: New Construction timing in comparable ZIP codes

New Construction permits in ZIP 60628 has 83 issued records, a 32 days median, and a 100 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6062832 days100 days83
ZIP 6064232 days120 days140
ZIP 6063035 days85 days121
ZIP 6064035 days130 days169
ZIP 6065736 days80 days325
ZIP 6061238 days94 days370
ZIP 6063138 days95 days77
ZIP 6062040 days97 days39