New Construction permits in ZIP 60628
The median new construction permit wait in ZIP 60628 was 32 days, based on 83 issued records.
Records checked832021–Sep. 15, 2026
The short answer
Typical wait32 daysmedian issued permit
Usually within100 days75% of records
Long-wait edge161 days90% of records
Evidence83issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 21 | 0 days | 3 days | 66 days |
| 2023 | 18 | 32 days | 32 days | 129 days |
| 2025 | 21 | 81 days | 107 days | 128 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.