Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

New Construction permits in ZIP 60640

The median new construction permit wait in ZIP 60640 was 35 days, based on 169 issued records.

Records checked1692021–Sep. 15, 2026

The short answer

Typical wait35 daysmedian issued permit
Usually within130 days75% of records
Long-wait edge258 days90% of records
Evidence169issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
27.2%
1–7 days
9.5%
8–30 days
11.8%
31–90 days
20.1%
91+ days
31.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021370 days35 days167 days
20224011 days113 days212 days
20232332 days68 days262 days
20242075 days133 days256 days
20252272 days194 days452 days
2026*2796 days178 days246 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable ZIP codes

ReportMedian75% withinRecords
ZIP 6063035 days85 days121
ZIP 6064035 days130 days169
ZIP 6065736 days80 days325
ZIP 6061238 days94 days370
ZIP 6062832 days100 days83
ZIP 6063138 days95 days77
ZIP 6064232 days120 days140
ZIP 6062040 days97 days39