ZIP boundary report
Permit processing times in ZIP 60640
Across 3,963 issued permits assigned to ZIP 60640, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60640, 3,963 issued permit records show a median processing time of 2 days; 75% were issued within 21 days and 90% within 79 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Permit processing times in ZIP 60640: wait distribution
For Permit processing times in ZIP 60640, 3,963 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60640: annual permit timing
Permit processing times in ZIP 60640 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,963 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 748 | 0 days | 10 days | 70 days |
| 2022 | 756 | 0 days | 7 days | 54 days |
| 2023 | 712 | 1 day | 13 days | 69 days |
| 2024 | 611 | 7 days | 29 days | 89 days |
| 2025 | 660 | 7 days | 31 days | 96 days |
| 2026* | 476 | 7 days | 35 days | 96 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60640: ZIP codes with similar overall timing
Permit processing times in ZIP 60640 has 3,963 issued records, a 2 days median, and a 21 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60640 comparisons
The Permit processing times in ZIP 60640 cohort contains 3,963 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 34 daysEasy Permit Process 0 daysSigns 24 daysElevator Equipment 0 daysNew Construction 35 daysWrecking & Demolition 0 daysReinstated Permit 0 daysScaffolding 0 days