Permit processing times in ZIP 60649
Across 2,475 issued permits assigned to ZIP 60649, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60649, 2,475 issued permit records show a median processing time of 2 days; 75% were issued within 15 days and 90% within 74 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60649: wait distribution
For Permit processing times in ZIP 60649, 2,475 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60649: annual permit timing
Permit processing times in ZIP 60649 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,475 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 439 | 0 days | 7 days | 61 days |
| 2022 | 459 | 0 days | 9.5 days | 49 days |
| 2023 | 437 | 1 day | 15 days | 121 days |
| 2024 | 462 | 6 days | 20 days | 78 days |
| 2025 | 408 | 5.5 days | 18 days | 68 days |
| 2026* | 270 | 6 days | 26 days | 84 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60649: ZIP codes with similar overall timing
Permit processing times in ZIP 60649 has 2,475 issued records, a 2 days median, and a 15 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60649 comparisons
The Permit processing times in ZIP 60649 cohort contains 2,475 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 2 daysRenovation & Alteration 34 daysEasy Permit Process 0 daysElevator Equipment 0 daysNew Construction 1 dayReinstated Permit 0 daysSigns 28 days