ZIP boundary report
Permit processing times in ZIP 60637
Across 4,374 issued permits assigned to ZIP 60637, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60637, 4,374 issued permit records show a median processing time of 2 days; 75% were issued within 19 days and 90% within 76 days, covering January 2021 through September 15, 2026.
The median was 0.5 days faster than the previous 12 months.
Permit processing times in ZIP 60637: wait distribution
For Permit processing times in ZIP 60637, 4,374 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60637: annual permit timing
Permit processing times in ZIP 60637 has 6 publishable issue-year cohorts spanning 2021–2026, representing 4,374 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 993 | 0 days | 5 days | 40 days |
| 2022 | 837 | 0 days | 5 days | 54 days |
| 2023 | 733 | 1 day | 21 days | 79 days |
| 2024 | 735 | 7 days | 34 days | 84 days |
| 2025 | 623 | 8 days | 36 days | 90 days |
| 2026* | 453 | 8 days | 36 days | 104 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60637: ZIP codes with similar overall timing
Permit processing times in ZIP 60637 has 4,374 issued records, a 2 days median, and a 19 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60637 comparisons
The Permit processing times in ZIP 60637 cohort contains 4,374 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 22 daysEasy Permit Process 0 daysNew Construction 19 daysElevator Equipment 0 daysSigns 28 daysReinstated Permit 0 daysWrecking & Demolition 0 days