Official community area
Kenwood permit processing times
For 1,044 issued permits in Kenwood, the median processing time was 6 days; 75% were issued within 24 days.
Records checked1,0442021–Sep. 15, 2026
The short answer
Typical wait6 daysmedian issued permit
Usually within24 days75% of records
Long-wait edge87 days90% of records
Evidence1,044issued permits
The median was 1 day slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 189 | 1 day | 21 days | 51 days |
| 2022 | 162 | 1 day | 13 days | 58 days |
| 2023 | 213 | 1 day | 23 days | 106 days |
| 2024 | 186 | 11 days | 30 days | 108 days |
| 2025 | 171 | 10 days | 26 days | 70 days |
| 2026* | 123 | 9 days | 31 days | 93 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Nearby points in the citywide timing distribution
| Report | Median | 75% within | Records |
|---|---|---|---|
| Kenwood | 6 days | 24 days | 1,044 |
| Oakland | 6 days | 27 days | 316 |
| Riverdale | 6 days | 64 days | 207 |
| Pullman | 5 days | 25 days | 686 |
| Near North Side | 4 days | 20 days | 14,726 |
| West Town | 4 days | 32 days | 7,607 |
| East Garfield Park | 3 days | 28 days | 1,600 |
| Grand Boulevard | 3 days | 34 days | 1,871 |