Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Kenwood

The typical express permit program permit issued in Kenwood took 5 days. The 75th-percentile wait was 15 days.

Records checked4482021–Sep. 15, 2026

The short answer

Typical wait5 daysmedian issued permit
Usually within15 days75% of records
Long-wait edge25 days90% of records
Evidence448issued permits

The median was 1 day slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
30.1%
1–7 days
30.4%
8–30 days
31.5%
31–90 days
7.1%
91+ days
0.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021400 days8.8 days29 days
2022270 days2 days14 days
2023610 days8 days25 days
20241186 days17 days23 days
20251248 days16 days32 days
2026*784.5 days15 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Kenwood5 days15 days448
Douglas4 days14 days426
Oakland6 days14 days126
Near North Side3 days13 days7,432
Pullman3 days15 days364
Bridgeport2 days8.2 days692
East Garfield Park2 days8 days616
Grand Boulevard2 days9 days676