Express Permit Program permits in Oakland

The typical express permit program permit issued in Oakland took 6 days. The 75th-percentile wait was 14 days.

Records checked1262021–Sep. 15, 2026

The short answer

Typical wait6 daysmedian issued permit
Usually within14 days75% of records
Long-wait edge36 days90% of records
Evidence126issued permits

The median was 6 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
23.8%
1–7 days
36.5%
8–30 days
27.0%
31–90 days
11.1%
91+ days
1.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021121 day7.8 days17 days
2022130 days3 days60 days
20231510 days27 days61 days
2024228.5 days26 days41 days
2025416 days14 days27 days
2026*233 days6 days13 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Oakland6 days14 days126
Kenwood5 days15 days448
Douglas4 days14 days426
Near North Side3 days13 days7,432
Pullman3 days15 days364
Bridgeport2 days8.2 days692
East Garfield Park2 days8 days616
Grand Boulevard2 days9 days676