Express Permit Program permits in Oakland
The typical express permit program permit issued in Oakland took 6 days. The 75th-percentile wait was 14 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in Oakland, 126 issued permit records show a median processing time of 6 days; 75% were issued within 14 days and 90% within 36 days, covering January 2021 through September 15, 2026.
The median was 6 days faster than the previous 12 months.
Express Permit Program permits in Oakland: wait distribution
For Express Permit Program permits in Oakland, 126 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in Oakland: annual permit timing
Express Permit Program permits in Oakland has 6 publishable issue-year cohorts spanning 2021–2026, representing 126 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 12 | 1 day | 7.8 days | 17 days |
| 2022 | 13 | 0 days | 3 days | 60 days |
| 2023 | 15 | 10 days | 27 days | 61 days |
| 2024 | 22 | 8.5 days | 26 days | 41 days |
| 2025 | 41 | 6 days | 14 days | 27 days |
| 2026* | 23 | 3 days | 6 days | 13 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in Oakland: Express Permit Program timing in comparable community areas
Express Permit Program permits in Oakland has 126 issued records, a 6 days median, and a 14 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Oakland | 6 days | 14 days | 126 |
| Kenwood | 5 days | 15 days | 448 |
| Douglas | 4 days | 14 days | 426 |
| Near North Side | 3 days | 13 days | 7,432 |
| Pullman | 3 days | 15 days | 364 |
| Bridgeport | 2 days | 8.2 days | 692 |
| East Garfield Park | 2 days | 8 days | 616 |
| Grand Boulevard | 2 days | 9 days | 676 |
More Express Permit Program permits in Oakland comparisons
The Express Permit Program permits in Oakland cohort contains 126 issued records; related links retain separate location and permit-category cohorts.
All Oakland permits Area reportExpress Permit Program citywide Type report