Oakland permit processing times
For 316 issued permits in Oakland, the median processing time was 6 days; 75% were issued within 27 days.
Records checked3162021–Sep. 15, 2026
The short answer
Typical wait6 daysmedian issued permit
Usually within27 days75% of records
Long-wait edge121 days90% of records
Evidence316issued permits
The median was 8.5 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 62 | 3 days | 79 days | 161 days |
| 2022 | 54 | 0 days | 8.8 days | 88 days |
| 2023 | 43 | 4 days | 27 days | 134 days |
| 2024 | 56 | 16 days | 37 days | 98 days |
| 2025 | 66 | 6.5 days | 17 days | 55 days |
| 2026* | 35 | 3 days | 12 days | 67 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Nearby points in the citywide timing distribution
| Report | Median | 75% within | Records |
|---|---|---|---|
| Kenwood | 6 days | 24 days | 1,044 |
| Oakland | 6 days | 27 days | 316 |
| Riverdale | 6 days | 64 days | 207 |
| Pullman | 5 days | 25 days | 686 |
| Near North Side | 4 days | 20 days | 14,726 |
| West Town | 4 days | 32 days | 7,607 |
| East Garfield Park | 3 days | 28 days | 1,600 |
| Grand Boulevard | 3 days | 34 days | 1,871 |