Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Kenwood

The typical renovation & alteration permit issued in Kenwood took 47 days. The 75th-percentile wait was 108 days.

Records checked2332021–Sep. 15, 2026

The short answer

Typical wait47 daysmedian issued permit
Usually within108 days75% of records
Long-wait edge171 days90% of records
Evidence233issued permits

The median was 38 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
13.7%
1–7 days
10.7%
8–30 days
15.9%
31–90 days
28.3%
91+ days
31.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20213533 days52 days102 days
2022381.5 days38 days74 days
20235558 days115 days186 days
20244769 days132 days180 days
20252894 days151 days175 days
2026*3090 days118 days175 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Kenwood47 days108 days233
North Park47 days120 days213
Norwood Park47 days105 days356
Near South Side48 days106 days238
Archer Heights48 days104 days109
Avalon Park46 days104 days161
Belmont Cragin48 days117 days389
Lower West Side48 days118 days560