Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in North Park

The typical renovation & alteration permit issued in North Park took 47 days. The 75th-percentile wait was 120 days.

Records checked2132021–Sep. 15, 2026

The short answer

Typical wait47 daysmedian issued permit
Usually within120 days75% of records
Long-wait edge263 days90% of records
Evidence213issued permits

The median was 6.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
20.7%
1–7 days
9.9%
8–30 days
12.7%
31–90 days
21.1%
91+ days
35.7%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214828 days104 days219 days
2022433 days38 days169 days
20233852 days124 days269 days
20243581 days176 days274 days
20253058 days154 days374 days
2026*19103 days144 days254 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Kenwood47 days108 days233
North Park47 days120 days213
Norwood Park47 days105 days356
Near South Side48 days106 days238
Archer Heights48 days104 days109
Avalon Park46 days104 days161
Belmont Cragin48 days117 days389
Lower West Side48 days118 days560