Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Belmont Cragin

The typical renovation & alteration permit issued in Belmont Cragin took 48 days. The 75th-percentile wait was 117 days.

Records checked3892021–Sep. 15, 2026

The short answer

Typical wait48 daysmedian issued permit
Usually within117 days75% of records
Long-wait edge209 days90% of records
Evidence389issued permits

The median was 29 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.0%
1–7 days
11.1%
8–30 days
11.6%
31–90 days
26.2%
91+ days
32.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021794 days80 days156 days
20227821 days102 days209 days
20237545 days110 days199 days
20246863 days164 days237 days
20255456 days116 days175 days
2026*3584 days144 days206 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Archer Heights48 days104 days109
Belmont Cragin48 days117 days389
Lower West Side48 days118 days560
South Lawndale48 days115 days504
Near South Side48 days106 days238
Kenwood47 days108 days233
North Park47 days120 days213
Norwood Park47 days105 days356