Renovation & Alteration permits in Avalon Park
The typical renovation & alteration permit issued in Avalon Park took 46 days. The 75th-percentile wait was 104 days.
Records checked1612021–Sep. 15, 2026
The short answer
Typical wait46 daysmedian issued permit
Usually within104 days75% of records
Long-wait edge173 days90% of records
Evidence161issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 28 | 5 days | 43 days | 91 days |
| 2022 | 42 | 38 days | 81 days | 138 days |
| 2023 | 19 | 69 days | 182 days | 440 days |
| 2024 | 26 | 42 days | 73 days | 126 days |
| 2025 | 23 | 78 days | 126 days | 233 days |
| 2026* | 23 | 85 days | 140 days | 193 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avalon Park | 46 days | 104 days | 161 |
| West Englewood | 46 days | 113 days | 540 |
| Brighton Park | 45 days | 113 days | 234 |
| Kenwood | 47 days | 108 days | 233 |
| North Park | 47 days | 120 days | 213 |
| Norwood Park | 47 days | 105 days | 356 |
| West Elsdon | 45 days | 119 days | 76 |
| Near South Side | 48 days | 106 days | 238 |