Renovation & Alteration permits in West Elsdon
The typical renovation & alteration permit issued in West Elsdon took 45 days. The 75th-percentile wait was 119 days.
Records checked762021–Sep. 15, 2026
The short answer
Typical wait45 daysmedian issued permit
Usually within119 days75% of records
Long-wait edge229 days90% of records
Evidence76issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 12 | 1.5 days | 13 days | 40 days |
| 2022 | 21 | 0 days | 75 days | 140 days |
| 2023 | 13 | 41 days | 90 days | 120 days |
| 2024 | 12 | 83 days | 180 days | 371 days |
| 2025 | 10 | 164 days | 332 days | 379 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Brighton Park | 45 days | 113 days | 234 |
| West Elsdon | 45 days | 119 days | 76 |
| West Englewood | 46 days | 113 days | 540 |
| Avalon Park | 46 days | 104 days | 161 |
| Clearing | 44 days | 114 days | 107 |
| Douglas | 44 days | 120 days | 157 |
| Hermosa | 44 days | 102 days | 182 |
| New City | 44 days | 116 days | 526 |