Signs permits in ZIP 60661
The median signs permit wait in ZIP 60661 was 21 days, based on 145 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Signs permits in ZIP 60661, 145 issued permit records show a median processing time of 21 days; 75% were issued within 44 days and 90% within 99 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Signs permits in ZIP 60661: wait distribution
For Signs permits in ZIP 60661, 145 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Signs permits in ZIP 60661: annual permit timing
Signs permits in ZIP 60661 has 6 publishable issue-year cohorts spanning 2021–2026, representing 145 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 27 | 6 days | 34 days | 132 days |
| 2022 | 26 | 7.5 days | 84 days | 146 days |
| 2023 | 32 | 8.5 days | 24 days | 47 days |
| 2024 | 21 | 45 days | 67 days | 70 days |
| 2025 | 24 | 39 days | 44 days | 65 days |
| 2026* | 15 | 22 days | 31 days | 38 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs permits in ZIP 60661: Signs timing in comparable ZIP codes
Signs permits in ZIP 60661 has 145 issued records, a 21 days median, and a 44 days 75th-percentile wait in this release.