Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

New Construction permits in ZIP 60661

The median new construction permit wait in ZIP 60661 was 21 days, based on 41 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked412021–Sep. 15, 2026

The short answer

For New Construction permits in ZIP 60661, 41 issued permit records show a median processing time of 21 days; 75% were issued within 51 days and 90% within 124 days, covering January 2021 through September 15, 2026.

Typical wait21 daysmedian issued permit
Usually within51 days75% of records
Long-wait edge124 days90% of records
Evidence41issued permits

Not enough records for a year-over-year comparison.

New Construction permits in ZIP 60661: wait distribution

For New Construction permits in ZIP 60661, 41 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
19.5%
1–7 days
12.2%
8–30 days
26.8%
31–90 days
26.8%
91+ days
14.6%

Change over time

New Construction permits in ZIP 60661: annual permit timing

New Construction permits in ZIP 60661 has 2 publishable issue-year cohorts spanning 2021–2022, representing 24 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211430 days72 days89 days
20221018 days38 days93 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction permits in ZIP 60661: New Construction timing in comparable ZIP codes

New Construction permits in ZIP 60661 has 41 issued records, a 21 days median, and a 51 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6066121 days51 days41
ZIP 6063719 days75 days397
ZIP 6062618 days127 days34
ZIP 6061416 days84 days399
ZIP 6060715 days70 days319
ZIP 6062215 days91 days292
ZIP 6062515 days73 days255
ZIP 6065413 days58 days98