Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60647

The median express permit program permit wait in ZIP 60647 was 1 day, based on 1,969 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,9692021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60647, 1,969 issued permit records show a median processing time of 1 day; 75% were issued within 8 days and 90% within 25 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge25 days90% of records
Evidence1,969issued permits

The median was 0.5 days faster than the previous 12 months.

Express Permit Program permits in ZIP 60647: wait distribution

For Express Permit Program permits in ZIP 60647, 1,969 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
41.7%
1–7 days
32.1%
8–30 days
18.6%
31–90 days
6.0%
91+ days
1.5%

Change over time

Express Permit Program permits in ZIP 60647: annual permit timing

Express Permit Program permits in ZIP 60647 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,969 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212080 days4.2 days13 days
20221970 days3 days18 days
20232030 days2.5 days21 days
20244922 days10 days28 days
20255033 days12 days32 days
2026*3663 days10 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60647: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60647 has 1,969 issued records, a 1 day median, and a 8 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606021 day9 days1,021
ZIP 606031 day9 days1,124
ZIP 606051 day10 days1,055
ZIP 606081 day7 days1,903
ZIP 606091 day7 days1,621
ZIP 606121 day7 days1,543
ZIP 606131 day8 days1,095
ZIP 606141 day9 days2,934