Express Permit Program permits in ZIP 60626
The median express permit program permit wait in ZIP 60626 was 1 day, based on 778 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60626, 778 issued permit records show a median processing time of 1 day; 75% were issued within 7 days and 90% within 22 days, covering January 2021 through September 15, 2026.
The median was 2 days slower than the previous 12 months.
Express Permit Program permits in ZIP 60626: wait distribution
For Express Permit Program permits in ZIP 60626, 778 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60626: annual permit timing
Express Permit Program permits in ZIP 60626 has 6 publishable issue-year cohorts spanning 2021–2026, representing 778 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 79 | 0 days | 0 days | 5.4 days |
| 2022 | 88 | 0 days | 0 days | 9.9 days |
| 2023 | 71 | 0 days | 8 days | 37 days |
| 2024 | 201 | 1 day | 8 days | 24 days |
| 2025 | 198 | 2 days | 9 days | 23 days |
| 2026* | 141 | 3 days | 10 days | 25 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60626: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60626 has 778 issued records, a 1 day median, and a 7 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60626 comparisons
The Express Permit Program permits in ZIP 60626 cohort contains 778 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60626 permits ZIP reportExpress Permit Program citywide Type report